As a manufacturer you are responsible to produce and control parts according to the requirements stated in Order Confirmation and in enclosed drawings.
Please check the quality of the parts in the order you produced:
Quality Control | ||
All tests should be performed in accordance to actual version of ISO 2859-1 | ||
The following sampling should be performed during production process (not after production) | ||
Parts in the order | Parts to be inspected | How many parts must pass the QC? (AQL 2.5) |
2-15 | 2 | 2 |
16-25 | 3 | 3 |
26-90 | 5 | 4 |
91-150 | 8 | 7 |
151-280 | 13 | 12 |
281-500 | 20 | 19 |
501-1200 | 32 | 30 |
1201-3200 | 50 | 47 |
Actions once you found defected part
- Stop the defected parts and send them to rework/repair
- Take second sample batch and make the checks once again.
- If the both results fit in AQL 2,5 the whole batch can be released
- Don't forget to remove nonconformities in all parts that were stopped before
If at least one result of checks exceeds AQL 2.5, the whole batch must be stopped and 100% QC with selection must be performed